Driveway Permits in New Jersey
A New Jersey driveway can involve up to three layers of government: the municipality for the driveway itself, the county for a county road, and NJDOT for a state highway. The paving on your own lot is almost always a town matter, and the town's answer can be very different from its neighbor's.
Updated · Figures and rules on this page link to the public sources they come from (listed below).
The municipality decides most jobs
Look at how three New Jersey towns treat the same overlay. Montclair's Planning and Community Development office issues a zoning permit for paving or re-paving a driveway; Hillsborough says another layer with no expansion needs no zoning permit; Holland Township charges $25 for a same-footprint job, $100 to modify a driveway or pave a stone one, and $300 plus a $500 escrow for a new driveway.
Work in the street is a separate permit. Middletown's road opening permit covers driveway widening, curb replacement and apron replacement, and Chatham Township requires a permit before any road opening, including new curbing.
| Town | Overlay on the same footprint | Source of the rule |
|---|---|---|
| Montclair (Essex) | Zoning permit required | Montclair 311 knowledge base |
| Hillsborough (Somerset) | No zoning permit without expansion | Hillsborough Township FAQ |
| Holland Township (Hunterdon) | $25 permit with survey | Holland Township driveway paving form |
County roads
When the driveway meets a county road, the county engineer has a say. Holland Township sends owners on a county road to Hunterdon County for the permit, and Morris County's road opening permit lists driveway construction among the work it covers, asks for a call 24 hours before construction starts and allows no permanent paving between December 1 and April 1.
Morris County's form also sets insurance minimums for the permittee and holds a three-year maintenance bond, or 20 percent of the deposit, after the work, so ask your paver who will hold the permit and the bond.
State highways and NJDOT
Driveways onto state highways fall under N.J.A.C. 16:47, the State Highway Access Management Code. Its fee table lists a single-family residential driveway at $60 for the application and $25 for the permit, with a $25 renewal per lot.
An NJDOT construction permit is not valid until the permittee gets a New Jersey One-Call confirmation number and gives it to the issuing office, and the permittee must give 72 hours' notice before starting. NJDOT permits are recorded with the county and stay with the property rather than the applicant.
Stormwater thresholds
New Jersey's stormwater rules apply their major development standards when a project disturbs one acre or more, or creates a quarter acre or more of new regulated impervious or motor vehicle surface. The rule's definitions exclude milling and repaving from disturbance, so a resurfacing job on the existing footprint is not counted.
Before anyone digs
New Jersey One Call must be contacted at least three full business days before digging, with weekends and holidays excluded. A tear-out, a regrade or a new apron all qualify, so the paver's markout request belongs in the schedule.
New Jersey driveway permit questions
Who issues a driveway permit in New Jersey?
Usually your municipality. A county road adds the county engineer, and a state highway adds NJDOT under N.J.A.C. 16:47.
Can a New Jersey county stop winter paving?
Morris County's road opening permit allows no permanent paving from December 1 to April 1, so apron work on a Morris County road waits for spring.
Do I need a New Jersey One Call markout for a driveway?
Yes, if there will be digging. Contact One Call at least three full business days before, and NJDOT won't validate a construction permit without the confirmation number.
Related paving services
- Asphalt Driveway Installation
- Asphalt Overlays and Top Coats
- Driveway Crack and Pothole Repair
- All paving services
Estimates by area
Sources
- Montclair 311: Do I need a permit to pave my driveway?
- Hillsborough Township: Do I need a permit to top coat my driveway?
- Holland Township: Driveway paving permits
- Middletown Township: Road opening permit
- Chatham Township: When is a permit needed?
- Morris County: Road opening permit (2025)
- N.J.A.C. 16:47-4.6, permits and permit fees
- N.J.A.C. 7:8-1.2, stormwater definitions
- New Jersey One Call
Let a local paver sort out the permit